How do i add extra sprints?
I have a Gantt Chart with dependencies enabled. When I shift the entire start date of the project all the dates shift appropriately so I believe it's working well. I've just inserted a new row and assigned a Predecessor Row and Duration. The bar appears to the right and dependency lines are drawn. However the Start and End…
I' ve just started trying to use Smartsheet as a project planning tool. I have created a Gantt chart for my project, and put in the resources. Where tasks are fully or partly completed I have put in the % Complete figure. The system does not seem to have adjusted the start and finish date of tasks that are not 100%…
你好家伙内容用户,我是厕所king to track hours in a day to maximize bandwidth per employee (OCR Racing & Building Obstacles). Unfortunately, Smartsheet doesn't have the ability to track hours in a day and to accurately display this in a Gantt Chart so I am looking for recommendations/tips, best practices, etc.…
Hi Everyone, I basically only use day as duration and don't need hours as time interval. I found it was kind of annoying when I drag the bar in Gantt Chart to adjust the duration, becuase it is based on hourly increment. I have to move the mouse very carefully to locate the start or end of the bar at the day but not hour.…
This post is in regards to this post below. I would like to get in touch with Jeremy michels to see if he will share the sheets he references with me.Any help will be appreciatedThanks so muchLouise Jeremy Michels601 ptsApril 5, 2015 8:30 pm I do the added columns now. We use it for both schedule and budget reasons. If you…
Hi, I am an architect and I NEED to see all the data graphically. I am looking for samples of project pipeline graphics produced using Smartsheet. Please, post them here or send me a link. Thanks! ileana
I have a task for a project that should be completed on Friday. The following Monday, I have a milestone (meeting) to review that task (proposal), The completion of the task on Friday is the predecessor for the milestone on Monday, but as soon as I set that predecessor, the milestone is moved to Friday too. I can't figure…
How do you easily set recurring tasks and meetings in Gantt view and Calendar? Example: Phone meeting or email updates, every 2nd and 4th week of the month?
Bonjour, Je ne trouve pas le moyen pour faire une ligne avec des dates réccurentes (par exemple réunion tous les mardi à 15h ou tous les 1er mardi du mois). Merci de votre aide.