Most of our projects include M-F working dates, however at the end of each project there is often a conference or event which may take place over a weekend or other non-working day. I'd love to be able to override and enter tasks on weekends for these instances without turning the entire project into a 7-day work week project and accidentally having other tasks "pushed" onto a weekend by mistake. Is there a way to override?
Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
I have a date and duration calculating problem where a task of 6 days duration is behaving in an odd manner when I try to use your prefix 'e' solution to "override" Sat and Sun as non-work days within Project Settings.
Grid and Calendar Views both show 7 days Duration instead of the specified/required 6 days, and Gantt View shows just 5 days.
Nevermind, I resolved it!<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"},{"tagID":335,"urlcode":"sheet-summary","name":"Sheet Summary"}]},{"discussionID":107817,"type":"question","name":"How to get the formulas to correctly count the completed tasks?","excerpt":"The current formula counts every task for the total. =COUNTIF(DESCENDANTS([Planning Done]@row), 1) + \" of \" + COUNT(CHILDREN([Task\/Topic]@row)) + \" Done\" I have been trying to get it to only count when all subtask from its proper row have been completed. There are 4 tasks and over 60 subtasks. When the subtasks are…","snippet":"The current formula counts every task for the total. =COUNTIF(DESCENDANTS([Planning Done]@row), 1) + \" of \" + COUNT(CHILDREN([Task\/Topic]@row)) + \" Done\" I have been trying to get…","categoryID":322,"dateInserted":"2023-07-19T19:04:08+00:00","dateUpdated":"2023-07-19T19:16:18+00:00","dateLastComment":"2023-07-19T19:40:18+00:00","insertUserID":163690,"insertUser":{"userID":163690,"name":"Ruvalcaba12","url":"https:\/\/community.smartsheet.com\/profile\/Ruvalcaba12","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-19T20:44:23+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":163690,"lastUserID":163690,"lastUser":{"userID":163690,"name":"Ruvalcaba12","url":"https:\/\/community.smartsheet.com\/profile\/Ruvalcaba12","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-19T20:44:23+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":6,"countViews":41,"score":null,"hot":3379592666,"url":"https:\/\/community.smartsheet.com\/discussion\/107817\/how-to-get-the-formulas-to-correctly-count-the-completed-tasks","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107817\/how-to-get-the-formulas-to-correctly-count-the-completed-tasks","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":107817,"commentID":386077,"name":"Re: How to get the formulas to correctly count the completed tasks?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/386077#Comment_386077","dateInserted":"2023-07-19T19:40:18+00:00","insertUserID":163690,"insertUser":{"userID":163690,"name":"Ruvalcaba12","url":"https:\/\/community.smartsheet.com\/profile\/Ruvalcaba12","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-19T20:44:23+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/2N6H1QH5FWDV\/screenshot.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"ScreenShot.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-19T19:24:31+00:00","dateAnswered":"2023-07-19T19:19:24+00:00","acceptedAnswers":[{"commentID":386066,"body":"