is it possible to include a critical path in the report ?
is it possible to include a critical path in the report or in dashboard ? Unless there's some other way to get it out of the sheet into another sheet ?
Answers
-
Genevieve P. Employee AdminThecritical pathis specific to each individual sheet or project, so it's not visible in a Report (although you are able to make Reports show Gantt view).
You could display one sheet's critical path by embedding aPublished Viewof the sheet into a Dashboard with theWeb Content Widget (see here), but again, this would only be for one specific sheet.
If you're looking to have some key data across many sheets in one overview sheet, you couldcopy/paste the key rowsinto a summary Sheet by using选择性粘贴and Cell-Linking in the data so that it stays live and updates when the source sheet updates. (See here for more information on cell-linking.)Keep in mind though that if you copy over certain rows and then create new dependencies, it could update the dates in the sheet which would erase the cell-linking to the original project, since the original project/source sheet has different dependencies than this sheet.
I hope this helps!
Cheers,
Genevieve
Help Article Resources
Categories
=COUNTIFS(PNS@row, 1) + COUNTIFS(EIP@row, 1) + COUNTIFS(Facilities@row, 1) + COUNTIFS([Patient Care Experience]@row, 1)<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"formulas","name":"Formulas"}]},{"discussionID":109375,"type":"question","name":"Calculate number of days and years from start date","excerpt":"I need to see how long staff have been with us, their tenure. I need this for any given dates, meaning \"today\". I have the start date, how do I get the days from that in years and days? Example: Start date is 06\/01\/2020, today is 08\/23\/2023 so the Tenure should be 3 years, 2 months, 22 days. I would take 3.2","snippet":"I need to see how long staff have been with us, their tenure. I need this for any given dates, meaning \"today\". I have the start date, how do I get the days from that in years and…","categoryID":322,"dateInserted":"2023-08-24T01:42:08+00:00","dateUpdated":null,"dateLastComment":"2023-08-24T15:05:11+00:00","insertUserID":82351,"insertUser":{"userID":82351,"name":"Leann Gibson","url":"https:\/\/community.smartsheet.com\/profile\/Leann%20Gibson","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/drupal_profile\/files\/2019-04\/7e\/c6\/n7ec6db531603daaefab20990ddcfdd53.jpg","dateLastActive":"2023-08-24T15:03:59+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"},"updateUserID":null,"lastUserID":82351,"lastUser":{"userID":82351,"name":"Leann Gibson","url":"https:\/\/community.smartsheet.com\/profile\/Leann%20Gibson","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/drupal_profile\/files\/2019-04\/7e\/c6\/n7ec6db531603daaefab20990ddcfdd53.jpg","dateLastActive":"2023-08-24T15:03:59+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":33,"score":null,"hot":3385732039,"url":"https:\/\/community.smartsheet.com\/discussion\/109375\/calculate-number-of-days-and-years-from-start-date","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/109375\/calculate-number-of-days-and-years-from-start-date","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":109375,"commentID":392349,"name":"Re: Calculate number of days and years from start date","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/392349#Comment_392349","dateInserted":"2023-08-24T15:05:11+00:00","insertUserID":82351,"insertUser":{"userID":82351,"name":"Leann Gibson","url":"https:\/\/community.smartsheet.com\/profile\/Leann%20Gibson","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/drupal_profile\/files\/2019-04\/7e\/c6\/n7ec6db531603daaefab20990ddcfdd53.jpg","dateLastActive":"2023-08-24T15:03:59+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-08-24T15:05:21+00:00","dateAnswered":"2023-08-24T15:05:11+00:00","acceptedAnswers":[{"commentID":392349,"body":"
That worked perfectly, thank you!!<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"formulas","name":"Formulas"}]},{"discussionID":109369,"type":"question","name":"INDEXING and Validating","excerpt":"I have a perplexing question, that I am sure someone knows and I am missing here. I am working on a sheet to gather data from a form. However, this form will get quite lengthily and may span multiple years. With that said this is where I am stumped. =INDEX(COLLECT({Test Sheet 1 Range 1}, {Test Sheet 1 Range 1}, <> \"//www.santa-greenland.com/community/discussion/73110/\"),…","snippet":"I have a perplexing question, that I am sure someone knows and I am missing here. I am working on a sheet to gather data from a form. However, this form will get quite lengthily…","categoryID":322,"dateInserted":"2023-08-23T21:21:49+00:00","dateUpdated":null,"dateLastComment":"2023-08-24T14:04:04+00:00","insertUserID":163519,"insertUser":{"userID":163519,"name":"Frank Hammond","title":"Mr.","url":"https:\/\/community.smartsheet.com\/profile\/Frank%20Hammond","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/avatarstock\/nWVKDFTEFOKBN.png","dateLastActive":"2023-08-24T15:23:34+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":163506,"lastUser":{"userID":163506,"name":"JamesB","title":"IT Project Manager","url":"https:\/\/community.smartsheet.com\/profile\/JamesB","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/avatarstock\/nEQMY42MFGXWS.png","dateLastActive":"2023-08-24T14:09:02+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":37,"score":null,"hot":3385713353,"url":"https:\/\/community.smartsheet.com\/discussion\/109369\/indexing-and-validating","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/109369\/indexing-and-validating","format":"Rich","lastPost":{"discussionID":109369,"commentID":392314,"name":"Re: INDEXING and Validating","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/392314#Comment_392314","dateInserted":"2023-08-24T14:04:04+00:00","insertUserID":163506,"insertUser":{"userID":163506,"name":"JamesB","title":"IT Project Manager","url":"https:\/\/community.smartsheet.com\/profile\/JamesB","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/avatarstock\/nEQMY42MFGXWS.png","dateLastActive":"2023-08-24T14:09:02+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-08-23T21:50:04+00:00","dateAnswered":"2023-08-23T21:43:36+00:00","acceptedAnswers":[{"commentID":392246,"body":"